Skip to content

MBI prend position sur les tarifs douaniers et leur impact sur la construction modulaire. Lire la déclaration ici.

District scolaire unifié de Beaumont - Agrandissement du lycée de Beaumont

Company: Silver Creek Modular
Location: Beaumont, CA, USA
Gross Size of Project: 59, 722 Square Feet
Days to Complete: 526

Critères d'attribution

Excellence architecturale

A design assist project approach was utilized on this project to allow the design architect and the modular building design team to collaborate on design considerations during the conceptual phase of the project which ensured that the modular construction systems selected would support the design intent. The project consists of two separate modular buildings which are each approximately 30,000 GSF. When combined the buildings contains 30 standard classrooms, 4 science laboratories, 2 medical training classrooms, 2 robotics classrooms, 2 multipurpose/collaboration
spaces, a full administrative wing and support spaces. The buildings’ exterior features multicolored stucco finishes, perforated aluminum screen walls and large glazing system. The buildings’ interior features abundant natural light in every educational space, custom wall graphics and custom wood paneling. The completed project reflects the coordinated efforts of all team members to provide a design focused experience.

Innovation technique et durabilité

To meet the project requirements a series of project specific module designs were utilized. The 12’-0” wide modules varied in length up to 48’-0”and the heights varied up to 14’-10”. The buildings feature 26’ tall breezeways at several locations which use specialized modules without a diaphragm at the 2nd level to create the open volume. A light weight concrete floor system was poured the in the factory for all modules. High efficiency LED lights with occupancy sensing controls and automatic daylighting
controls were used in all spaces. Dimming controls were provided in all classrooms to allow the teachers to adjust the light levels for specific learning exercises. Wall assemblies separating classrooms and adjacent spaces were designed to provide acoustic separation. Low-VOC materials were used throughout the project to provide a healthy learning environment. High efficiency VRF space conditioning systems were utilized with a dedicated outside air ventilation system.

Rapport coût-efficacité

Le maître d'ouvrage a reconnu dès le début du processus de planification que la construction modulaire était la méthode de construction la plus rentable pour son projet d'agrandissement du campus. En utilisant la construction hors site, il a également été en mesure de réaliser des avantages significatifs en termes de calendrier par rapport aux méthodes de construction traditionnelles. Au cours du processus de conception, les espaces intérieurs ont été soigneusement planifiés afin de maximiser le travail pouvant être effectué dans l'usine, dans la mesure du possible. Dans la mesure du possible, les toilettes ont été conçues et placées de manière à être entièrement contenues dans un module, afin que ces espaces puissent être achevés en usine.

Voir d'autres lauréats des prix de distinction

Pour voir tous nos lauréats actuels, visitez notre page principale sur les prix.