Modular by Design: Turning Architecture into a Manufacturing System

Max Gennis

Max Gennis is a partner in the Construction Law Practice Group at WeirFoulds LLP

Matt-Gaulton_Website_300x300

Matt Gaulton is an associate in the Construction Law Practice Group at WeirFoulds LLP.

Modular construction is gaining popularity in Canada. In 2025, the Canadian modular construction market was valued at $5.5 billion CAD, up from $5.1 billion CAD in 2024.[1] The multifamily sector was the strongest, generating approximately $2.48 billion CAD, with a compound annual growth rate (“CAGR”) of 7.3%. The commercial sector generated approximately $701 million CAD, followed by the education sector at approximately $624 million CAD. The lodging sector generated approximately $235 million CAD, but its forecasted CAGR of 6.1% is nearly 3% higher than the CAGR for conventional construction in this sector.[2]

Overall, modular construction represents 5.5% of the Canadian construction market and is expected to grow at a CAGR of 5.2%, exceeding the overall construction rate by 1.0%.[3]

Using modular construction in the right circumstances can benefit a project, including by providing greater predictability in pricing, better quality control, shorter schedules, and improved safety.[4] Modular projects, however, have unique features that must be accounted for. It would be a mistake to assume that a standard form construction contract will adequately address these sorts of projects. Parties planning a modular project should consider the following key areas when preparing and negotiating their contracts:

Upfront Payments and Milestones

Modular projects require a significant upfront investment of funds before anything arrives on-site. Modular contractors often require early payments to cover costs related to, among other things, factory setup and material procurement. Traditional contracts often assume payment as work progresses, which does not necessarily align with modular processes. To keep the contractor’s cash flow healthy (and the work on schedule) while protecting the owner’s interests, consider the following approaches:

  • Milestone Payments: Structure the payment schedule around tangible and measurable production milestones rather than relying solely on on-site progress. In some cases, a deposit on signing may be appropriate to provide the contractor with funds to start fabrication.
  • Advance Payment Security: If advance payments are made before modules are delivered, this increases risk for the owner, including if the contractor becomes insolvent. The contract should clearly address when and how ownership of the materials and modules transfers to the owner. In addition, the owner should consider requiring performance security such as bonding or an irrevocable, standby letter of credit. Before agreeing to any advance payments, the parties should discuss them with sureties and lenders to ensure their approval.

Factory Inspection and Quality Assurance Rights

Quality control is critical on a modular project. On traditional projects, owners inspect work on the job site, but with modular projects, much of the work happens at a remote facility. Contracts should address how and when the owner (and its consultants) can inspect the fabrication facility to monitor progress and quality. This might include periodic inspections during production and a final factory acceptance check before modules ship. This must be balanced, however, with the contractor’s ability to perform the work without excessive disruption, and the requirement that visitors respect factory rules, such as those addressing confidentiality of trade secrets and safety requirements.

The parties should agree on a plan to inspect and test work at the factory prior to delivery, and how to address any observed deficiencies. Contractors may require inspection and sign-off at the factory for each module, subject to any damage that occurs during shipment. Obtaining owner approval before shipping modules can be beneficial, since deficiencies are easier to fix in the factory than on-site. The contract will also need to establish a plan for inspection after installation on-site, and clear guidelines on when final acceptance of the work will occur.

Delivery Schedule and Storage

Delivering large modules requires careful coordination. Delays in site readiness or other scheduling hiccups could result in completed modules sitting in the factory (or in storage yards) longer than anticipated. It is wise to address storage and delivery timing in the contract to avoid disputes over who bears cost and risk if modules are not delivered promptly when ready. Parties should consider the following in their contract:

  • How long finished modules can remain at the factory: The parties may agree on a set number of days that the modules can remain at the factory, and how compensation will work if the modules need to be stored for longer than expected.
  • Storage location and conditions: Owners will also want to make sure that the conditions and security at the storage site are appropriate, considering the investment they have made in the modules.
  • Separation of modules within the factory: Factories or storage locations may have modules from different projects and owners. Modules should be labelled and separated.

In addition, the parties should address risk of loss during storage and transit. Transportation of modules is complex and carries risk, such as potential moisture damage.[5] The contract should clearly allocate responsibility for modules between the factory and the site. The parties should also discuss insurance considerations for storage and transit with their respective insurance advisors and reflect these arrangements in the contract.

Other Considerations

Payment terms, inspection and quality assurance, and delivery and storage, are all important considerations for any modular project, but there are many more. For example:

  • Permitting and approvals: How will these responsibilities be divided among the parties? Separate permits and approvals may be needed for fabrication and on-site construction. The goal is to avoid confusion or finger-pointing by explicitly stating who handles each required permit or approval in the contract.
  • Differences between jurisdictions: The parties should give thought to potential issues that may arise when manufacturing and on-site assembly take place in different jurisdictions. For example, laws, codes, regulations and approval processes may vary by province and municipality. Parties should ensure compliance with all applicable requirements in each relevant jurisdiction.[6]
  • Project requirements: All stakeholders should be familiar with project requirements before construction begins. These requirements should be clearly stated, incorporated as contract documents, and developed collaboratively from early in the design process to maximize the likelihood of project success.[7]
  • Transportation Logistics: Building the modules is half the battle. Once fabricated, they need to be delivered to site. Aside from risk of loss during transportation, which is discussed earlier in this article, transporting modules over long distances presents logistical challenges, such as requiring specialized vehicles and permits. The complexity may be compounded if the contractor is transporting modules between provinces or countries. The parties should prepare for these challenges as soon as possible and reflect the appropriate requirements in their contract.[8]
  • Tariffs: It is essential to consider the impact of tariffs on any project where materials may be imported from other countries. The parties should set out in their contract how changes in tariffs will be managed and who bears the risk.
  • Insurance: As mentioned above, parties should consult with their insurance advisors to determine specific insurance requirements for modular projects, including with respect to fabrication, materials, transportation, and assembly.

Conclusion: Setting the Stage for Success

The increase in modular construction is an exciting development for project delivery that provides the opportunity for significantly improved outcomes on construction projects. It also has the potential to address societal issues such as the need for affordable housing.[9] Stakeholders should resist the urge to shoehorn their modular project into their existing contract forms. By addressing the timing of payments, factory inspections, storage logistics, and the other issues discussed above, parties can reduce risk on their modular projects and set the stage for success. While this article focuses on prime contract rights between an owner and contractor, many of the same considerations will apply for modular subcontractors of all tiers.

To date, while certain organizations have published standardized contract forms for modular and prefabricated projects, the Canadian Construction Documents Committee (“CCDC”) and the Canadian Construction Association (“CCA”) have not. This means that for parties who use these forms, robust supplementary conditions will need to be prepared. Whether a company uses its own form of contract or prefers standardized forms, it should work with experienced legal counsel who understands the unique needs of modular construction.

Starting a modular project with a well-developed contract protects both the owner and the contractor. It will help keep the project on track and on budget, and it will improve quality from the factory floor to final installation on-site. With the right contractual framework in place, parties can fully reap the benefits of modular construction while confidently managing its unique challenges.

[1] Modular Building Institute, 2026 Canadian Modular Construction Industry Report, online: https://www.modular.org/industry-analysis/.

[2] Modular Building Institute, 2026 Canadian Modular Construction Industry Report, online: https://www.modular.org/industry-analysis/.

[3] Modular Building Institute, 2026 Canadian Modular Construction Industry Report, online: https://www.modular.org/industry-analysis/.

[4] Carolyn Whitzman, Lauren Shiga & Priya Perwani, Scaling Up Modular Construction (Toronto: School of Cities, University of Toronto, August 2024), online: https://schoolofcities.utoronto.ca/wp content/uploads/2024/11/Scaling-up-Modular-Construction-EN_August-2024_1.pdf, page 6.

[5] Supra note 4, page 15.

[6] Supra note 4, page 10.

[7] Supra note 4, page 14.

[8] Supra note 4, page 16.

[9] Supra note 4, page 7.

Plus de Modular Advantage

Mind the Gap: The Interface Between Onsite and Offsite Construction

Every design for manufacture and assembly (DfMA) project — modular, mass timber, or panelized — is really two projects joined at a seam. One is built in a controlled factory to millimeter tolerances; the other in the field, in weather, to the looser tolerances of poured concrete and human hands. Between them sits an interface: where the factory’s precision meets the site’s reality.

Rules, Rails & Repeatability: Applying DfMA to Modular Healthcare

DfMA offers several advantages for healthcare projects, with faster delivery among the most valuable. Schedule matters when building new facilities, expanding campuses, renovating existing space or bringing care closer to communities that need it.

Precision and Possibility: Demands of DfMA and What Modular Mass Timber Makes Possible

Mass timber does not automatically create an efficient modular building. Its precision makes early coordination more important: fabricated components will accurately reproduce both the team’s solutions and its mistakes. The material’s advantages are realized only when supported by an equally precise design and delivery process.

Catch It in the Factory, Not in the Field: Smarter Testing for Modular Builds

Integrating watertightness and airtightness testing into factory workflows transforms quality assurance from a reactive process into a proactive commissioning strategy. It ensures that every module shipped is field ready and resilient for transportation while also supporting the ability of the modular construction industry to make buildings better.

Modular by Design: Turning Architecture into a Manufacturing System

Modular construction is often presented as a faster way to build. Speed, however, is only one part of its value. The larger opportunity is to create a coordinated design and production system that improves quality, reduces uncertainty, and allows a building to move efficiently from concept design through manufacturing, transportation, installation, and completion.

Repeatability Begins with Trust: What Alora at Dry Creek Reveals About Scaling Modular Housing

Alora at Dry Creek, a 329-unit, multifamily community comprising five four-story buildings in Centennial, Colorado, demonstrates how repeatable design, standardized manufacturing and early collaboration can work together to create a model that is not only faster to deliver, but easier to replicate across future projects.

T.R. Arnold: The Art of Third-Party Inspections

T.R. Arnold (TRA), a third-party inspection company in Elkhart, Indiana, contracts with modular manufacturers across the US. Manufacturers register with each state to which they intend to send their modules and may be required to hire a third-party inspection company.

Creating an ‘Ecosystem for Innovation:’ 50+ Years of Modular Construction Oversight in Virginia

Virginia’s modular building program began in 1973, with the implementation of the Virginia Industrialized Building Unit and Mobile Home Safety Regulations. Now it’s leading the country in modular code adoption.

Understanding Thermal Barriers Compliance Methods & Emerging NFPA-275 Foam Plastic Technologies

New fire barrier technologies are improving total costs and margins in major areas of construction, such as commercial, government, union and prevailing wage projects. These benefits translate into other large fringe areas, such as agriculture, commercial cold storage facilities, grow houses, outbuildings, military and aviation hangars.

Financing the Future of Modular Construction: How Better Capital Strategies Can Help the Industry Scale

The future of construction will not be solved by one product, one lender, or one financing model. It will be solved by matching the right project with the right capital strategy.