UMass Amherst Family Housing Phases 1&2
Company: Signature Building Systems
Location: Amherst, Massachusetts
Gross Size of Project: 139200 Square Feet
Days to Complete: 172
Critères d'attribution
Excellence architecturale
Phases 1 & 2 of the UMass Family Housing Project each consist of 12 buildings, totaling 240 2BR + 1BA apartments for students with children. Manufactured by Signature Building Systems, each dwelling unit consists of ~1,100 SF of living area configured from two volumetric modules.
A total of 264 modules encompassing 139,200 SF were fabricated by SBS, transported, and erected during Phases 1 &2. Standard apartments are vertically stacked townhouse-style with a fully-equipped kitchen, dining room, living room, and utility room on the first level. Two bedrooms and a full bath are located on the second level. ADA apartments are horizontally joined ranch-style, and include LR, DR, utility room, two BRs, and fully-accessible kitchen and bath.
Innovation technique et durabilité
Pour ce premier bâtiment, il a fallu 60 jours entre la première mise en service et l'achèvement de l'érection. Au fur et à mesure de l'avancement du projet, notre équipe a réduit ce délai à 45 jours entre la première mise en ligne et l'achèvement. Cette approche rapide et de haute qualité de la construction a permis à nos clients d'occuper le premier bâtiment le 12 août 2022, soit 25 semaines seulement après le début de la fabrication modulaire.
Rapport coût-efficacité
Nous attendons une réponse officielle de notre client concernant le rapport coût-efficacité.